| Project |
PTML (Ufone) Expansion of GSM 900\1800 Networks and allied systems Phase III & Phase IV |
| Salient Feature |
Completed 23 BTS Sites all over Sindh, Including BTS Room, D.G set Room; lattice Tower and electro-mechanical Installation Complete in all respect to date. Presently busy in executing Six (3) BTS Sites in interior Sindh. |
| Consultant \ Vendor |
Nortel Networks (Asia) Limited |
| |
|
| Project |
Telenor Phase II & Phase III |
| Salient Feature |
Completed 34 BTS Sites all over Sindh, Including, Site acquisition, commercial power installation, BTS Room, D.G set pads; lattice Tower and electro-mechanical Installation Complete in all respect to date. |
| Consultant \ Vendor |
Siemens AG and Siemens Pakistan |
| |
|
| Project |
Strength evaluation & Strengthening of Spray Draying Plant Jamshoro. Clariant Pakistan (Pvt.) Limited |
| Salient Feature |
Structural analysis, Design & Strengthening of Spray Draying Plant |
| Consultant \ Vendor |
Turkey Project |
| Completion Date |
April 04 |
| |
|
| Project |
Himalaya Feeds (Pvt.) Limited. Shahbaz pur Road, Rahimyar Khan |
| Salient Feature |
Factory Building , Administration Building, Feeds Storage facilities , under ground Tanks, Road, Parking facilities and Plant Installation and Commissioning |
| Consultant \ Vendor |
Turkey Project |
| Completion Date |
January 04 |
| |
|
| Project |
Al-Saeed Floor Mill Jamesabad |
| Salient Feature |
Factory Building and Plant Installation and Commissioning |
| Consultant \ Vendor |
Turkey Project |
| Completion Date |
November 03 |